From the Laos Shipyard – Anouvong in the Making

We’re happy to confirm that construction on Heritage Line Anouvong in Laos’s Bokeo Province is coming along. From the very first moment steel is cut and placed, the entire building process takes approximately two years before Anouvong’s first journey along the upper Mekong River in Laos.

22 April 2019: The keel laying ceremony marks the formal beginning of the ship’s construction. This ritual is held to bless the vessel, captain and crew with good fortune over its lifetime. The keel is the bottom-most structural component, running along the center from bow to stern, and it keeps the ship stabilized as it moves through the water.

May 2019: After the keel is laid, hull assembly (the ship’s main body) begins with setting the framework and deck beams.

June and July 2019: Construction commences on the bottom deck of the vessel (the hold), which is typically beneath the water line, as well as the main passenger deck.

August 2019: After the main deck is Heritage Line Anouvong’s topmost level, the terrace deck.

September 2019: A construction worker cuts a beam atop the roof of the terrace deck.

With the hull nearing construction, the next planned stage will involve mounting the engine and generator during the month of October.

Stay tuned to our website and social media channels for more updates on Heritage Line Anouvong’s construction process!